Analisis Perbandingan Biaya dan Waktu Rigid Pavement antara Cast In Situ dengan Precast Menggunakan Metode AHP pada Proyek Peningkatan Ruas Jalan Banyakan - Tiron, Kabupaten Kediri, Jawa Timur

Ilmam Ardiansyah, Michella Beatrix

Abstract


The development of infrastructure in land transportation, namely roads, is one of the supports for economic growth in Indonesia. Road Functional Worthiness is the condition of a road section that meets the technical requirements for suitability to provide security and safety for its users as well as administrative requirements that provide legal certainty for Road Operators and Road users so that the Road can be operated for the public. The Banyakan – Tiron section is a road section in the district Kediri is the access road for Dhoho International Airport, Kediri. This research aims to determine the type of pavement that is more efficient and effective in the continuation of the Banyakan - Tiron road improvement project by comparing in terms of cost and time between the Precast Prestress Concrete Pavement (PPCP) method and the Cast in Situ method. The results of the analysis using the AHP method were obtained in terms of costs, according to respondents who preferred the Cast in Situ (CiS) method with a percentage of 80% and the CiS cost was IDR 7,693,476,000.00, while for Precast Prestress Concrete Pavement (PPCP) it was 20% with a cost of Rp. 9,292,262,000.00, Meanwhile, in terms of time between Conventional and Precast Prestress Concrete Pavement (PPCP), it is concluded that the PPCP implementation time is shorter than CiS with a percentage of 62% for PPCP and 38% for CiS from the calculation that PPCP implementation takes 29 days faster than CiS with 106 days while CiS takes 135 days.

Keywords


Cast in Situ (CiS); Precast Prestress Concrete Pavement (PPCP) ; Analytical Hierarchy Process (AHP)

References


Aji, I. P. (2015). “Analisis faktor - faktor yang mempengaruhi kinerja biaya proyek subkontraktor pada PT X.” Master Tesis, ITS, Surabaya, 1–139.

Amdiya Huqbanl; Paikun; Cece Suhendi; Universitas Nusa Putra. (2020). Analysis of Material Delays in The Timeliness of Development. Jurnal Teknik Sipil Dan Lingkungan Universitas Nusa Putra (J-TESLINK, 1(2), 35–43. https://teslink.nusaputra.ac.id

Anggraini, E. A. (2019). Faktor-Faktor Yang Mempengaruhi Kinerja Biaya Dan Waktu Pada Proyek Konstruksi. Teknika: Jurnal Sains Dan Teknologi, 3(1), 11–22.

Karya, J., Sipil, T., Karya, J., & Sipil, T. (2014). Aplikasi rekayasa nilai. 3, 674–684.

Khade, V., & Wuppulluri, M. (2023). A comparative study on rigid and flexible magnetoelectric composites: Review. Journal of Advanced Dielectrics, May. https://doi.org/10.1142/S2010135X23400015

Kompetensi, P., & Sdm, T. (n.d.). Kementerian pekerjaan umum & perumahan rakyat direktorat jenderal bina konstruksi balai jasa konstruksi wilayah vi makassar.

Mukrimaa, S. S., Nurdyansyah, Fahyuni, E. F., YULIA CITRA, A., Schulz, N. D., غسان, د., Taniredja, T., Faridli, E. M., & Harmianto, S. (2016). No 主観的健康感を中心とした在宅高齢者における 健康関連指標に関する共分散構造分析Title. In Jurnal Penelitian Pendidikan Guru Sekolah Dasar (Vol. 6, Issue August).

Nandyanto, Y. U., Beatrix, M., & Triana, M. I. (2023). Analisa Pengendalian Mutu Proyek Gudang Pt Santos Jaya Abadi Menggunakan Process Decision Program Chart Method. Jurnal Teknik Sipil Dan Arsitektur, 28(2), 70–79. https://doi.org/10.36728/jtsa.v28i2.2566

Prisilia Ardananeswari. (2016). Model Analytical Hierarchy Process Untuk Penentuan Pemasok Produk Perawatan Tubuh Pada Pamella Swalayan 1 Yogyakarta. Journal Economy, 1–12.

Puji, T., Aditya, G., & Amal, A. S. (2022). Perbandingan Biaya Siklus Hidup Berdasarkan Jenis Perkerasan Pada Ruas Jalan Kabupaten Kediri. 19–25.

Riyandi, A., Bina, U., & Informatika, S. (2019). SATIN – Sains dan Teknologi Informasi System Pemilihan Vendor IT. 5(2).

Ruas, K., & Gurah, P. (2020). TUGAS AKHIR PERENCANAAN RIGID PAVEMENT BERBASIS “ PRECAST PRESTRESS CONCRETE PAVEMENT ” DITINJAU DARI SEGI BIAYA DAN WAKTU ( STUDI “ PRECAST PRESTRESS CONCRETE PAVE MENT .”

Setiawan, E. D. W. I. (2020). Program studi teknik sipil fakultas teknik universitas islam riau pekanbaru 2020. 1–59.

Umum, M. P. (2018). Peraturan Menteri Pekerjaan Umum Dan Perumahan Rakyat Republik Indonesia Nomor 07/Prt. M/2016 Tentang Penyelenggaraan Sistem Penyediaan …, 1–34.




DOI: http://dx.doi.org/10.30811/portal.v16i1.4667

Refbacks

  • There are currently no refbacks.


Copyright (c) 2024 Ilmam Ardiansyah, Michella Beatrix